Our Case Studies DNB Dump Steam Tunnel Supports

A pipe support survey and audit, completed by EASL, confirmed that two adjacent pipework supports were hitting their bottom stops. This was attributed to load transfer following historic work carried out on adjacent support during a previous outage. It was recommended that all three supports be replaced during the next outage. However, the supports could not be replaced without delaying the end of the outage resulting in significant delays and costs, through lost generating capacity, to the client.